Back Hangar Taxiway Rehabilitation Schedule - July 17 - 28

BACK HANGAR CONSTRUCTION

We have completed week six of back hangar area taxiway rehabilitation. We still have clean-up (striping, GSB88 and some specific approach work) but this essentially concludes the major back hangar area taxiway rehabilitation.

Next week, we will move into rehabilitation of Runway 3/21 and taxiway “A” east of taxiway “A2”.

TAXIWAY “A” AND RUNWAY 3/21 REHABILITATION

Week 7 – (July 17 – 21) We anticipate rehabilitating taxiway “A” east of taxiway “A2” to the west side of taxiway “F” and rehabilitating runway 3/21 during this week.

Week 8 – (July 24 – 28) We anticipate rehabilitating the remainder of taxiway “A” east of taxiway “F” to the threshold of runway 30 during this week.

We will update each week with the anticipated next two weeks of construction. (This information is also be located on the www.bozemanairport.com homepage) If you are an owner/contact for t-hangars, please pass on to the other tenants as we may or may not have their contact information. If you have any questions, please don’t hesitate to contact our offices at 406-388-6632.

ALSO, IF YOU HAVE ARRANGED TO HAVE A SEAL COAT FOR YOUR APPROACH, PLEASE BE ADVISED THIS WILL BE COMPLETED AT THE END OF THE PROJECT

About the Airport

Bozeman Yellowstone International Airport (BZN) is owned and operated by the Gallatin Airport Authority. Established in 1972, the function of the Gallatin Airport Authority is to plan for, provide, operate and safely maintain an aviation facility adequate to the needs of the flying public in the Yellowstone region and to keep it self-sustaining.